| A. Site Work & Civil |
| Site Clearing & Grubbing |
0.986 AC · Already cleared per property analysis |
$2,500/AC |
$2,465 |
| Rough Grading & Earthwork |
0.986 AC per CDs (minor grading, flat site) |
$8,000/AC |
$7,888 |
| Stormwater / Drainage System |
StormTech SC-310 per CDs · inlets + chamber system |
Lump Sum |
$85,000 |
| Sanitary Sewer Connections |
Toho Water Authority · stub-out on-site per CDs |
Lump Sum |
$28,000 |
| Water Main & Fire Service |
8" PVC main + fire hydrant + backflow assembly per CDs |
Lump Sum |
$35,000 |
| Asphalt Paving (Parking + Drive Lanes) |
0.56 AC on-site impervious · 1.5" Type S-III surface |
$4.50/SF |
$109,800 |
| Concrete Sidewalks & Curbing |
5' walks, Type C & D curbs, bollards per CDs |
$9.50/SF |
$42,750 |
| Landscaping & Irrigation |
Per L100/L200/LI100 plan — trees, sod, shrubs, auto irrigation |
Lump Sum |
$55,000 |
| Site Lighting (Poles & Fixtures) |
Per E001/E002 — Lithonia arm-mounted + building fixtures |
Lump Sum |
$28,000 |
| Signage (Monument + Directional) |
2 monument sign locations per E002 |
Lump Sum |
$18,000 |
| Site Work Subtotal |
|
|
$411,903 |
| B. Building Construction (Hard Costs) |
| Foundation / Slab-on-Grade |
13,500 SF footprint · 4" slab · spread footings |
$18/SF |
$243,000 |
| Structural Frame (Masonry / CMU / Steel) |
Two-story · load bearing masonry + steel at second floor |
$38/SF |
$513,000 |
| Exterior Skin (Stucco / Façade) |
Perimeter area approx. 11,200 SF of exterior wall |
$22/SF façade |
$246,400 |
| Roof System (TPO / Flat + Slope) |
6,750 SF roof deck · TPO membrane over insulation |
$18/SF |
$121,500 |
| Interior Framing, Drywall & Insulation |
Demising walls, corridor partitions, tenant dividers |
$14/SF |
$189,000 |
| Doors, Frames & Hardware |
Storefront glazing ground floor + office doors above |
$12/SF |
$162,000 |
| Flooring (Retail Shell + Office) |
Polished concrete shell F1; VCT/carpet tile F2 |
$9/SF |
$121,500 |
| Ceilings & Finishes |
2x4 ACT grid office / open retail shell F1 |
$8/SF |
$108,000 |
| Plumbing (Rough + Finish) |
Multi-tenant; restrooms per floor + retail stub-outs |
$22/SF |
$297,000 |
| HVAC (Rooftop Units + Distribution) |
Split commercial RTUs per floor; 13,500 SF total conditioned |
$28/SF |
$378,000 |
| Electrical (Service + Distribution + Lighting) |
Per E102 electrical plan — 400A+ commercial service, 2-panel |
$26/SF |
$351,000 |
| Fire Protection / Sprinklers |
Wet pipe NFPA 13 per Osceola County requirement |
$5.50/SF |
$74,250 |
| Elevators / Stairs |
1 commercial elevator + 2 interior stair assemblies (ADA req.) |
Lump Sum |
$95,000 |
| Miscellaneous & General Conditions |
Dumpster enclosure, bollards, temporary facilities, cleanup |
4% of above |
$115,527 |
| Building Hard Cost Subtotal |
|
~$224/SF avg. |
$3,015,177 |
| C. Contractor Overhead, Profit & Contingency |
| General Contractor Overhead & Profit |
Central FL market; mid-size commercial GC |
12% of hard costs |
$361,821 |
| Construction Contingency |
Standard for vertical commercial new construction |
8% of hard costs |
$241,214 |
| GC & Contingency Subtotal |
|
|
$603,035 |
| D. Soft Costs & Professional Fees |
| Architecture / Engineering Fees |
CDs already on file (buyer to re-engineer for code updates); est. partial re-stamp/update |
5% of hard costs |
$150,759 |
| Civil Engineering / Survey Updates |
Survey update, utility coordination, any access revisions |
Lump Sum |
$28,000 |
| Geotech / Environmental |
Phase I + borings (existing geo report from 2004 will need refresh) |
Lump Sum |
$18,500 |
| Legal / Title / Closing Costs |
Entity formation, title, doc stamps (excl. land acquisition) |
Lump Sum |
$22,000 |
| Project Management / Developer Fee |
Owner's rep or developer overhead |
3.5% of hard costs |
$105,531 |
| Marketing / Pre-Leasing |
Broker fees, LOIs, pre-construction leasing |
Lump Sum |
$35,000 |
| Soft Costs Subtotal |
|
|
$359,790 |
| E. Permits, Impact Fees & Government Charges |
| Osceola County Building Permit |
Based on construction valuation per Appendix A fee schedule (Oct 2025) |
~1.4% of valuation |
$52,000 |
| Plan Review Fees |
Commercial plan review, fire, zoning, environmental |
Lump Sum |
$18,000 |
| Osceola County Mobility Impact Fees |
New rates effective June 18, 2025 (significant increase — Office use ~$8,000–$12,000/1,000 SF est.) |
~$9/SF |
$121,500 |
| Water / Sewer Connection Fees (Toho) |
ERU-based; multi-tenant commercial building |
Lump Sum |
$42,000 |
| FDOT / ROW Permits (SR 192 adjacency) |
Required for any work within SR 192 ROW per CDs |
Lump Sum |
$8,500 |
| Permits & Impact Fees Subtotal |
|
|
$242,000 |
| F. Construction Financing (Interest Reserve) |
| Construction Loan Interest Reserve |
~$3.5M loan at 8.25% for 18-month build period (avg. 60% drawn) |
Lump Sum |
$259,875 |
| Loan Origination / Closing Costs |
1.5 points on construction loan |
1.5% |
$52,500 |
| Financing Subtotal |
|
|
$312,375 |
| Total Development Cost (Excl. Land) |
|
$334/SF blended |
$4,944,280 |
| + Land Acquisition (Recommended List Price) |
|
$32.00/SF land |
$1,375,000 |
| Total All-In Development Cost |
|
$460/SF blended |
$6,319,280 |